"It hasn't stopped developments from being able to tie in," Deputy City Administrator Shawn Cox told Community Impact this August. "It's just we're not going to tie in a large subdivision to it because it can't handle that."
That quote shapes most of the new construction in Dripping Springs right now. The city's main treatment plant is close to full. Bigger subdivisions have had to find their own way to handle wastewater, and each way comes with its own timeline, its own operator and often its own tax or assessment layer. Two new homes at the same price, a few miles apart, can cost very different amounts to carry each year. One may sit in a phase that is ready to close and the other in a phase on hold. You find this out by reading utility agreements and district records. Listing photos won't show it.
A plant sized for a smaller town
The South Regional Wastewater Reclamation Facility is Dripping Springs' main treatment plant. As of August 2026 its treatment capacity was about 162,500 gallons per day. Community Impact reported on August 28 that it had been near capacity for several months and could not accept most new large connections. The city's wastewater customer count grew about 600% from 2015 to 2026.
The fix has been in the works for more than a decade. The city applied for a Texas Pollutant Discharge Elimination System permit in 2015, and TCEQ granted it in 2019. The Save Our Springs Alliance then sued over possible discharges into Onion Creek. On April 11, 2025, the Texas Supreme Court ruled for TCEQ and the city. The permit allows up to 822,500 gallons per day. The settlement conditions described in the court's opinion include no discharge until flows exceed 399,000 gallons per day, plus UV disinfection. Utilities Director Gray Lahrman has said the city plans to discharge only in an emergency and will store treated wastewater that can't be used for irrigation.
The schedule has slipped. In April 2025, phase one was forecast to finish in September 2027. The August 2026 plan reads this way:
- February 2026: City Council selected three firms for the expansion.
- July 2026: The Texas Water Development Board approved $53 million in additional funding.
- December 2026: Planned notice to proceed for phase one.
- 2027: Phase one construction begins.
- Around 2029: Phase one is complete, according to Lahrman's estimate of two and a half to three years of construction.
That gives a buyer shopping in October 2026 a window of about three years. During that time, new homes mostly come from subdivisions that brought their own answer to the wastewater question.
Five ways a subdivision is getting sewer service
The city's monthly utility reports to its Utility Commission name the projects. The table below draws on the reports for January and April 2026. Treat it as a spring 2026 snapshot, because statuses change month to month.
| Development | Wastewater arrangement | Status in city reports |
|---|---|---|
| Village Grove | Pump-and-haul, operated by a third-party contractor | Completed and ready for final inspection, April 2026 |
| Anarene, also called Double L | A "321 plant" designed to convert to land application at a set threshold of living-unit equivalents, or LUEs | Phase 1 construction started; irrigation field design under discussion |
| Big Sky Ranch | Interim land-application system | Phase 3 accepted at 54,300 gallons per day |
| Carter Ranch | Pump-and-haul under negotiation | Utility installation underway |
| Fellers–Tri Point | Requesting pump-and-haul for 18 homes | Will eventually be served by the West Interceptor line |
| Wild Ridge, also called Cynosure | Not yet settled | Site work started; water and wastewater plans under review |
| Heritage | City connection by allocated LUEs | 480 LUEs total, 286 with certificates, 194 remaining; Phase 4 homes on hold until the discharge plant is operating |
Pump-and-haul means a storage tank that is emptied on a schedule and trucked away for treatment somewhere else. The city has approved only three pump-and-haul plans in recent years. Community Impact counts more than 3,800 lots or units across developments that are using these alternative approaches. A city project inventory lists New Growth at Roger Hanks at 240 residential units. According to Community Impact, the subdivision is waiting for the South Regional facility to gain capacity before it moves forward.
Look at Heritage in that table. Even a project with an approved city allocation can have a later phase that depends on infrastructure the city hasn't built yet. If you're buying a lot or a to-be-built home in a later phase, you're buying into that dependency, and your closing date and the builder's timeline rest on it.
The tax bill follows the pipe
Someone has to pay for a subdivision's wastewater system, its irrigation fields and its storage. In Dripping Springs that cost often shows up as a district tax or an assessment that sits on top of the county and school district lines.
The posted 2026 rates show how heavy that layer can be:
- Headwaters MUD: $0.90 per $100 of assessed value for tax year 2026, all of it debt service. The final plat for Headwaters at Barton Creek, Phase 4, Section 5, approved in February 2020, shows a MUD-owned and MUD-operated onsite treatment plant.
- Hays County Development District No. 1: an adopted 2026 total of $0.90, made up of $0.30 maintenance and operations, $0.44 debt service and $0.16 road tax.
- Dripping Springs MUD No. 1: $0.76 on Hays County's 2025 adopted rate sheet. A 2026 figure was not confirmed.
- City of Dripping Springs: a draft 2026 levy ordinance shows $0.2729, which recites passage on September 15, 2026. Check that figure against the final ordinance.
A $0.90 district rate on a home assessed at $500,000 comes to $4,500 a year before any other taxing unit is counted. That alone is more than three times the city's draft rate.
Heritage uses a different tool, a Public Improvement District. P3 Works' October 2025 bond materials refer to wastewater impact fees under a separate wastewater agreement with the developer. For Improvement Areas 3A and 3B, those materials projected an assessment equal to about $0.7586 per $100. That works out to roughly $3,616 per unit per year on average, with installments starting in 2027. The sample $420,000 home in the same document showed a $3,185.96 annual PID installment and a total overlapping rate-equivalent of $2.6206. These are projections. They are not a parcel bill. The Heritage PID's 2026 Annual Service Plan Update, dated August 18, 2026, updates the assessment rolls by parcel. It sets the 2026 installments due on January 31, 2027.
District boundaries overlap in ways a subdivision name won't tell you. The Caliterra wastewater agreement names Hays County Development District No. 1 as a party, for example. Still, the rate that applies to a given Caliterra address should be confirmed by parcel.
Caliterra shows how the deals are built
The Caliterra agreement shows how these arrangements work in practice. It reserves 674 LUEs for Caliterra and 286 for Ranch at Caliterra from the city's south regional facilities. The city also gets 389 LUEs of disposal and holding capacity for its own use. Ranch at Caliterra runs on a temporary land-application system operated by the district until the city can serve it. The agreement ties city service for Ranch at Caliterra to construction of the expansion. It also sets January 15, 2027 as the deadline for the city to award a construction bid.
So a home's long-term utility service can depend on a milestone in a contract between the city and a district. The homebuyer isn't a party to that contract, but it still affects the house.
City customers are paying more too
Homes already on the city system have a cost to plan for as well. In May 2026, City Council raised wastewater rates for the first time since 2022, effective on September bills. The residential base charge went from $28.88 to $43.32, and the usage rate from $4.05 to $5.67 per 1,000 gallons. At the average of 6,578 gallons a month, a household's bill goes from $55.52 to $80.62, an increase of more than 45%. The city is also raising its general fund contribution to wastewater from $980,000 to $2.5 million through 2030 to hold down customer fees.
That makes it a fair way to compare homes. A resale home on city sewer, a home in a MUD and a PID home each have a different monthly and annual cost, and each one can be calculated.
What belongs in your file before the option period ends
On a Dripping Springs property, especially new construction or a lot, these items are worth gathering early:
- The wastewater path for that parcel. Find out whether it is a city connection, a district plant, an interim land-application system or pump-and-haul, and who operates it.
- Phase status. Confirm the phase has its LUEs or certificates and isn't waiting on the expansion, the way Heritage Phase 4 was in early 2026.
- Every overlapping taxing unit and assessment for that specific parcel, using current-year rates. Don't rely on the subdivision's marketing.
- For PID properties, the current assessment roll entry. The Heritage update lists parcel-level rolls and a January 31 due date.
- Any city-district agreement deadlines that affect future service, such as Caliterra's January 15, 2027 bid-award date.
None of this is tax or legal advice for a particular situation. It's the paperwork that tells you what a Dripping Springs home will cost to own and when it will be ready.
Questions buyers ask
Is the moratorium still in effect?
No. The city's temporary development moratorium ran from 2021 to 2022 and was lifted while the litigation was still going, according to Community Impact. As of August 2026, the practical limit is that most large new residential connections aren't being accepted unless an agreement or special circumstance already exists.
Will the city discharge into Onion Creek?
The permit allows discharge under its conditions. The city's stated intent is to discharge only in an emergency.
When does the pressure ease?
Phase one is expected around 2029 if the December 2026 notice to proceed and the 2027 construction start hold. Lahrman said phase two will be designed while phase one is under construction.
If you're considering a Dripping Springs home, a lot or a builder contract that depends on a district plant, a PID assessment or a city capacity agreement, Eileen DePew will read the utility agreements, district records and assessment rolls with you before your option period ends. Get peace of mind when you sign. Schedule a consultation.